Evaporator, stop and safety valves
1. Remove the block of heating and К/В.
2. Remove expansion valve.
3. Loosen the clamps on the left and right sides and disconnect the hoses.
4. Take out from fastenings of draft.
When installing, bring both levers to the highest position and secure the rods.
5. Turn out all screws and wring out all clamps of the bottom part of the case. Remove the lower case and take out the evaporator.
6. Give union nuts (1) and remove the check valve (2).
When installing, replace the O-rings.
7. Remove the screws (1) and remove the safety valve (2).
When installing, replace the O-rings.
8. Installation is carried out in the reverse order.
Dryer tank
1. Discharge the A/C system.
2. Remove the right air cleaner.
3. Remove the bolts, pull up the suction and pressure pipes and block them if the air conditioner is left open for more than one hour.
When installing, replace the O-rings.
4. Remove the bolts and pull up the dryer reservoir.
5. Installation is carried out in the reverse order.